2013年8月13日星期二

Pass4Test provides information on the latest PMI CA0-001 examination training

Please select our Pass4Test to achieve good results in order to pass PMI certification CA0-001 exam, and you will not regret doing so. It is worth spending a little money to get so much results. Our Pass4Test can not only give you a good exam preparation, allowing you to pass PMI certification CA0-001 exam, but also provide you with one-year free update service.


Pass4Test IT expert team take advantage of their experience and knowledge to continue to enhance the quality of exam training materials to meet the needs of the candidates and guarantee the candidates to pass the PMI certification CA0-001 exam which is they first time to participate in. Through purchasing Pass4Test products, you can always get faster updates and more accurate information about the examination. And Pass4Test provide a wide coverage of the content of the exam and convenience for many of the candidates participating in the IT certification exams except the accuracy rate of 100%. It can give you 100% confidence and make you feel at ease to take the exam.


You can now get PMI CA0-001 exam certification our Pass4Test have the full version of PMI CA0-001 exam. You do not need to look around for the latest PMI CA0-001 training materials, because you have to find the best PMI CA0-001 training materials. Rest assured that our questions and answers, you will be completely ready for the PMI CA0-001 certification exam.


If you are looking for a good learning site that can help you to pass the PMI CA0-001 exam, Pass4Test is the best choice. Pass4Test will bring you state-of-the-art skills in the IT industry as well as easily pass the PMI CA0-001 exam. We all know that this exam is tough, but it is not impossible if you want to pass it. You can choose learning tools to pass the exam. I suggest you choose Pass4Test PMI CA0-001 exam questions and answers. I suggest you choose Pass4Test PMI CA0-001 exam questions and answers. The training not only complete but real wide coverage. The test questions have high degree of simulation. This is the result of many exam practice. . If you want to participate in the PMI CA0-001 exam, then select the Pass4Test, this is absolutely right choice.


In such society where all people take the time so precious, choosing Pass4Test to help you pass the PMI certification CA0-001 exam is cost-effective. If you choose Pass4Test, we promise that we will try our best to help you pass the exam and also provide you with one year free update service. If you fail the exam, we will give you a full refund.


Exam Code: CA0-001

Exam Name: PMI (Certified Associate in Project Management)

CA0-001 Free Demo Download: http://www.pass4test.com/CA0-001.html


NO.1 What is a tool to improve team performance?
A. Staffing plan
B. External feedback
C. Performance reports
D. Co-Location
Answer: D

PMI exam simulations   CA0-001   CA0-001   CA0-001   CA0-001 exam   CA0-001

NO.2 Who is responsible for determining which processes from the Process Groups will be employed and
who will be performing them?
A. Project sponsor and project manager
B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager
Answer: C

PMI questions   CA0-001 braindump   CA0-001 exam prep   CA0-001   CA0-001

NO.3 Which of the following processes is necessary to ensure that the project employs all processes
needed to meet its requirements?
A. Perform Quality Control
B. Quality Policy
C. Perform Quality Assurance
D. Quality Planning
Answer: C

PMI   CA0-001   CA0-001   CA0-001 dumps

NO.4 Which tool or technique measures performance of the project as it moves from project initiation
through project closure?
A. Resource leveling
B. Parametric measuring
C. Pareto chart
D. Earned value
Answer: D

PMI demo   CA0-001 exam prep   CA0-001   CA0-001   CA0-001

NO.5 You are assigned to implement the project control plan. What should you do to ensure the plan is
effective and current?
A. Perform periodic project performance reviews.
B. Identify quality project standards.
C. Follow ISO 9000 quality standards
D. Complete the quality control checklist.
Answer: A

PMI braindump   CA0-001   CA0-001 exam prep   CA0-001

NO.6 A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of
today, the actual expenditure is $1,200 and approximately half of the work has been completed.
What is the cost variance?
A. -$700
B. -$200
C. +$200
D. +$500
Answer: A

PMI braindump   CA0-001   CA0-001 answers real questions

NO.7 Scope verification is PRIMARILY concerned with which of the following?
A. Acceptance of the work deliverables.
B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.
Answer: A

PMI   CA0-001 exam dumps   CA0-001   CA0-001 answers real questions

NO.8 As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total
project cost. You should calculate the forecast using which of the following methods?
A. BAC
B. EAC
C. ETC
D. WBS
Answer: B

PMI   CA0-001   CA0-001   CA0-001   CA0-001

NO.9 Which of the following is an example of a risk symptom?
A. Failure to meet intermediate milestones
B. Force of nature, such as a flood
C. Risk threshold target
D. Crashing front loading or fast tracking
Answer: A

PMI   CA0-001   CA0-001

NO.10 Which tool is used to develop technical details within the project management plan?
A. Expert Judgment
B. Project Management Methodology
C. Project Management Information
D. Project Selection Methods
Answer: A

PMI original questions   CA0-001 test answers   CA0-001 exam prep   CA0-001 answers real questions

NO.11 Which activity is an input to the select sellers process?
A. Organizational process assets
B. Resource availability
C. Change control process
D. Team performance assessment
Answer: A

PMI certification   CA0-001 test questions   CA0-001   CA0-001 exam

NO.12 How is scheduled variance calculated using the earned value technique?
A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV
Answer: C

PMI exam   CA0-001   CA0-001

NO.13 Which of the following are outputs of the Monitor and Control Project Work process?
A. Requested changes, forecasts, recommended corrective actions
B. Forecasts, resources plan, bottom up estimating
C. Recommended corrective actions, cost baseline, forecasts
D. Requested changes, recommended corrective actions, project constraints
Answer: A

PMI   CA0-001   CA0-001 dumps   CA0-001   CA0-001 test

NO.14 On what is project baseline development established?
A. Approved product requirements
B. Estimated project cost and schedule
C. Actual project cost and schedule
D. Revised project cost and schedule
Answer: B

PMI test answers   CA0-001   CA0-001 answers real questions   CA0-001 practice test

NO.15 What is one of the MAJOR outputs of activity sequencing?
A. Responsibility assignment matrix
B. Work breakdown structure update
C. Project network diagram
D. Mandatory dependencies list
Answer: C

PMI   CA0-001 exam dumps   CA0-001 original questions   CA0-001 original questions   CA0-001 questions

NO.16 Who MUST know when a risk event occurs so that a response can be implemented?
A. Customers
B. Project sponsors
C. Project management team
D. Insurance claims department
Answer: C

PMI dumps   CA0-001 original questions   CA0-001   CA0-001 questions

NO.17 While implementing an approved change, a critical defect was introduced. Removing the defect will
delay the product delivery. What is the MOST appropriate approach to managing this situation?
A. Utilize the change control process.
B. Crash the schedule to fix the defect.
C. Leave the defect in and work around it.
D. Fast-track the remaining development.
Answer: A

PMI   CA0-001   CA0-001 braindump   CA0-001 demo   CA0-001   CA0-001

NO.18 During what process is the quality policy determined?
A. Initiating
B. Executing
C. Planning
D. Controlling
Answer: C

PMI pdf   CA0-001 certification   CA0-001 pdf   CA0-001 pdf

NO.19 Which of the following is an example of contract administration?
A. Negotiating the contract
B. Authorizing contractor work
C. Developing the statement of work
D. Establishing evaluation criteria
Answer: B

PMI answers real questions   CA0-001 answers real questions   CA0-001 dumps   CA0-001 certification training   CA0-001 questions

NO.20 What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
A. Pareto
B. Ishikawa
C. Shewart-Deming
D. Delphi
Answer: C

PMI   CA0-001   CA0-001   CA0-001 test answers   CA0-001

NO.21 Which process occurs within the Monitoring and Controlling Process Group?
A. Cost Control
B. Quality Planning
C. Quantitative Risk Analysis
D. Cost Budgeting
Answer: A

PMI exam   CA0-001 questions   CA0-001   CA0-001 practice test   CA0-001 test answers

NO.22 Information distribution involves making needed information available to project stakeholders in a timely
manner. What is an output from information distribution?
A. Earned value analysis
B. Trend analysis
C. Project records
D. Performance reviews
Answer: C

PMI   CA0-001 certification training   CA0-001 exam dumps   CA0-001   CA0-001

NO.23 The Define Scope process is in which of the following process groups?
A. Initiating
B. Planning
C. Monitoring & Controlling
D. Executing
Answer: B

PMI test   CA0-001   CA0-001 test   CA0-001 exam dumps   CA0-001 test questions

NO.24 Which of the following methods is a project selection technique?
A. Flowcharting
B. Earned value
C. Cost-benefit analysis
D. Pareto analysis
Answer: C

PMI   CA0-001   CA0-001   CA0-001   CA0-001

NO.25 The projectt management processes presented in the PMBOK Guide should:
A. Always be applied uniformly
B. Be selected as appropriate by the sponsor
C. Be selected as appropriate by the project team
D. Be applied based on ISO guidelines.
Answer: C

PMI   CA0-001   CA0-001 certification training   CA0-001

NO.26 Which type of analysis is used to develop the communications management plan?
A. Product
B. Cost benefit
C. Stakeholder
D. Research
Answer: C

PMI dumps   CA0-001   CA0-001   CA0-001 exam simulations   CA0-001   CA0-001 exam

NO.27 Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying
tangible components of each deliverable are all part of which of the following?
A. Work breakdown structure
B. Organizational breakdown structure
C. Resource breakdown structure
D. Bill of materials
Answer: A

PMI dumps   CA0-001   CA0-001 exam simulations   CA0-001 exam prep   CA0-001 test

NO.28 Which type of analysis is used to examine project results through time to determine if performance is
improving or deteriorating?
A. Control chart
B. Earned value
C. Variance
D. Trend
Answer: D

PMI   CA0-001 exam simulations   CA0-001 test

NO.29 How is quality control performed?
A. By identifying quality standards that are relevant to the project and determining how to satisfy them.
B. By monitoring specific project results in compliance with relevant quality standards and determining
corrective actions as needed.
C. By ensuring that the entire project team has been adequately trained in quality assurance processes.
D. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure
conformance to quality standards.
Answer: B

PMI   CA0-001   CA0-001   CA0-001 certification   CA0-001

NO.30 What is the definition of project plan execution?
A. Integrating all planned activities.
B. Performing the activities included in the plan.
C. Developing and maintaining the plan.
D. Execution of deliverables.
Answer: B

PMI exam simulations   CA0-001 demo   CA0-001 questions   CA0-001 dumps   CA0-001   CA0-001 dumps

More and more people choose PMI CA0-001 exam. Because of its popularity, you can use the Pass4Test PMI CA0-001 exam questions and answers to pass the exam. This will bring you great convenience and comfort. This is a practice test website. It is available on the Internet with the exam questions and answers, as we all know, Pass4Test is the professional website which provide PMI CA0-001 exam questions and answers.


没有评论:

发表评论