Pass4Test is a professional website. It focuses on the most advanced PMI PMI-002 for the majority of candidates. With Pass4Test, you no longer need to worry about the PMI PMI-002 exam. Pass4Test exam questions have good quality and good service. As long as you choose Pass4Test, Pass4Test will be able to help you pass the exam, and allow you to achieve a high level of efficiency in a short time.
Pass4Test will give you confidence to pass PMI PMI-002 test. Our Exam Preparation Material provides you everything the candidates will need to get the PMI-002 certification. Our PMI PMI-002 will provide you with exam questions with verified answers that reflect the actual exam. These questions and answers will help you to do preparation for taking a certification examination. High quality and Value for the PMI-002 Exam: 100% guarantee to Pass Your PMI PMI-002 exam and get your certification.
Since PMI PMI-002 certification is so popular and our Pass4Test can not only do our best to help you pass the exam, but also will provide you with one year free update service, so to choose Pass4Test to help you achieve your dream. For tomorrow's success, is right to choose Pass4Test. Selecting Pass4Test, you will be an IT talent.
Exam Code: PMI-002
Exam Name: PMI (Certified Associate in Project Management (CAPM) Certification)
One year free update, No help, Full refund!
Total Q&A: 748 Questions and Answers
Last Update: 2013-12-12
If you choose Pass4Test, success is not far away for you. And soon you can get PMI certification PMI-002 exam certificate. The product of Pass4Test not only can 100% guarantee you to pass the exam, but also can provide you a free one-year update service.
PMI-002 Free Demo Download: http://www.pass4test.com/PMI-002.html
NO.1 A contract cannot contain _____________.
A. Illegal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above
Answer: A
PMI PMI-002 braindump PMI-002 dumps
NO.2 The end of the project comes after which of the following?
A. Project charter
B. F'na' deliverable
C. Schedule
D. QA activities are done
Answer: B
PMI PMI-002 PMI-002
NO.3 Most change requests are a result of _______.
A. Value added change (enhancements)
B. Schedule constraints
C. Regulatory constraints
D. Improvement to the project scope
Answer: A
PMI exam PMI-002 answers real questions PMI-002 dumps PMI-002 PMI-002 PMI-002 study guide
NO.4 In PMBOK, the seller is ________ to the project team.
A. Internal
B. External
C. Outside
D. Assigned
Answer: B
PMI test answers PMI-002 dumps torrent PMI-002 original questions PMI-002
NO.5 The product description of a project can help to create procurement details. Which one of the
following best describes product description?
A. The product description defines the contracted work, based on the requirements of the
project customer
B. The product description defines the contracted work
C. The product description defines the requirements for the contract work
D. Al1 of the above
Answer: A
PMI PMI-002 pdf PMI-002 study guide PMI-002 test PMI-002 dumps
NO.6 A complete set of indexed project records is called __________.
A. Project archives
B. Index
C. sow
D. Project History
Answer: A
PMI PMI-002 pdf PMI-002 questions
NO.7 Create Procurement document is done in _______.
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements
Answer: A
PMI practice test PMI-002 exam PMI-002 practice test PMI-002
NO.8 You are project manager of a project. During the process of selecting the sellers, you reject
one vendor because it doesn't have the manufacturing capability. This is an example of which
selection tool?
A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment
Answer: B
PMI PMI-002 PMI-002 PMI-002
NO.9 Which one of the following comes first in the project plan?
A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan
Answer: A
PMI exam PMI-002 dumps torrent PMI-002 exam dumps
NO.10 ______________ provides details about how the project scope may be changed.
A. Control Scope system
B. VeiirV Scope
C. Scope Charter
D. Scope Management plan
Answer: D
PMI test questions PMI-002 dumps torrent PMI-002 test answers
NO.11 Which of the following provides the least accurate in estimating?
A. Rough order of magnitude
B. Budget estimate
C. WBS estimate
D. Definitive estimate
Answer: A
PMI test questions PMI-002 PMI-002 PMI-002 PMI-002
NO.12 Based on the PMBOK, who is ultimately responsible for the project quality?
A. Project team
B. Project manager
C. QA manager
D. Validation engineer
Answer: B
PMI PMI-002 questions PMI-002 demo PMI-002 exam
NO.13 Administrative Closure should occur ___________.
A. At the end of each phase of the project
B. At the end of the whole project
C. At the end of 50% of the project
D. At the end of 100% of the project
Answer: A
PMI PMI-002 exam PMI-002
NO.14 You are project manager and the monthly report to the client showed zero schedule variance.
However, member of the team know that a milestone has been missed which will cause an
overall delay to the project. Which one of the following is being inadequately reported?
A. Communication plan variance
B. Resource management plan
C. Critical path status
D. Risk analysis
Answer: C
PMI PMI-002 PMI-002 PMI-002 demo
NO.15 Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?
A. Precedence Diagramming Method (PDM)
B. Gant Cnart Diagram (GCD)
C. Dependency Diagramming Method (DDM)
D. Arrow Diagramming Method (ADM)
Answer: D
PMI demo PMI-002 exam simulations PMI-002 PMI-002
NO.16 Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are
examples of ____________.
A. Enterprise benefits measurement methods when selecting a project
B. Integral parts of the SOW
C. Ways to ensure stakeholder commitment
D. Project selection methods
Answer: A
PMI exam prep PMI-002 PMI-002
NO.17 What is the lowest level in a work breakdown structure?
A. Project task
B. w¡ãrl< packag
C. sow
D. None
Answer: B
PMI practice test PMI-002 PMI-002 pdf PMI-002
NO.18 In which phase project manager is assigned to a project?
A. During the initiation stage
B. During the planning stage
C. After approval of budget
D. After the project is proven feasible
Answer: A
PMI exam simulations PMI-002 PMI-002 PMI-002
NO.19 A Risk Register is a part of the ________.
A. Project Scope Statement
B. Project Management plan
C. Project Scheduling plan
D. Project Charter
Answer: B
PMI practice test PMI-002 study guide PMI-002 pdf
NO.20 What is a corrective action?
A. An action that brings future project events Into alignment with the project plan
B. An action to correct something in the project
C. An action to prevent something in the project
D. Corrective action is not related to project
Answer: A
PMI exam PMI-002 test answers PMI-002 PMI-002 exam dumps PMI-002 pdf PMI-002 study guide
NO.21 Project Quality Management includes:
A. Customer satisfaction
B. Prevention over inspection
C. Continuous improvement
D. Al1 of the above
Answer: D
PMI PMI-002 dumps PMI-002 certification training PMI-002
NO.22 Which of the following technique to identify the underlying cause of a problem and take steps
to prevent further occurrence?
A. Root cause analysis
B. Quality audits
C. Project audits
D. Risk audits
Answer: A
PMI practice test PMI-002 PMI-002 original questions
NO.23 You are managing a project that will implement a new Insurance software package. Two
project team members have difficulty working together. They come to you, for help resolving
the issues. You immediately set up a meeting that includes the functional manager. After the
meeting you and the functional manager discuss the issues and agree on a solution. What
type of organizational structure you are working in?
A. Functional
B. Balanced matrix
C. Piojectized
D. Strong Matrix
Answer: B
PMI certification training PMI-002 PMI-002 PMI-002 questions PMI-002 demo
NO.24 Who is responsible for issuing the project charter?
A. The project manager
B. The project sponsor
C. The Team lead
D. The nianagement
Answer: B
PMI test questions PMI-002 exam PMI-002 certification training
NO.25 Who has the responsibility for informing the final deliverable to all stakeholders?
A. Project Manager
B. Sponsor
C. Team Lead
D. Management
Answer: A
PMI exam simulations PMI-002 PMI-002 PMI-002 exam dumps PMI-002
NO.26 During the planning phase of your project, your project team members have discovered
another way to complete a portion of the project scope. This method is safer for the project
team, but may cost more for the customer. This is an example of _______.
A. Alternative identification