Pass4Test is continuing to provide the candidates with IT certification exam-related reference materials for years. Pass4Test.com is the website that is validated by all the test-takers, which can provide all candidates with the best questions and answers. Pass4Test comprehensively ensures the interests of all candidates, which enjoys immense praise of the candidates. Moreover Pass4Test is the most trusted website on the current market.
IT certifications are playing an important role in our career. In order to get a promotion and get more money, every IT people put more effort into their work. Instead this way, we can depend on our strength to won the boss's heart. Microsoft 070-178 certification is vitally important for IT people. In fact, the test is not difficult as you have imagined it. You only need to select the appropriate training materials. Pass4Test Microsoft 070-178 practice test will regularly update the exam dumps to fulfill your requirements. So, our Microsoft 070-178 test is the latest. Hurry up! You will achieve your aim.
To pass Microsoft 070-178 certification exam seems to be a very difficult task. Having registered 070-178 test, are you worrying about how to prepare for the exam? If so, please see the following content, I now tell you a shortcut through the 070-178 exam. The certification training dumps that can let you pass the test first time have appeared and it is Pass4Test Microsoft 070-178 exam dumps. If you would like to sail through the test, come on and try it.
Pass4Test provide you the product with high quality and reliability. You can free download online part of Pass4Test's providing practice questions and answers about the Microsoft certification 070-178 exam as a try. After your trail I believe you will be very satisfied with our product. Such a good product which can help you pass the exam successfully, what are you waiting for? Please add it to your shopping cart.
Pass4Test is the door to success. Pass4Test Microsoft 070-178 test questions are very similar to the actual test. At the same time, our Pass4Test Microsoft 070-178 test questions and test answers are studied, based on the same syllabus. And we are also constantly upgrading our training materials. So, pass rate is 100% and high quality guarantee!
Microsoft 070-178 exam is an popular examination of the IT industry , and it is also very important. We prepare the best study guide and the best online service specifically for IT professionals to provide a shortcut. Pass4Test Microsoft 070-178 exam covers all the content of the examination and answers you need to know . Tried Exams ot Pass4Test , you know this is something you do everything possible to want, and it is really perfect for the exam preparation.
Exam Code: 070-178
Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2014-01-16
Have you ever used Pass4Test Microsoft 070-178 dumps? The braindump is latest updated certification training material, which includes all questions in the real exam that can 100% guarantee to pass your exam. These real questions and answers can lead to some really great things. If you fail the exam, we will give you FULL REFUND. Pass4Test practice test materials are used with no problem. Using Pass4Test exam dumps, you will achieve success.
070-178 Free Demo Download: http://www.pass4test.com/070-178.html
NO.1 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A
Microsoft 070-178 exam 070-178
NO.2 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C
Microsoft study guide 070-178 070-178 original questions
NO.3 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D
Microsoft demo 070-178 070-178 questions 070-178 exam prep 070-178 certification
NO.4 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C
Microsoft dumps torrent 070-178 070-178 070-178 braindump 070-178 070-178 pdf
NO.5 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
Microsoft 070-178 070-178 070-178 original questions
NO.6 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
Microsoft demo 070-178 exam dumps 070-178 070-178
NO.7 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C
Microsoft 070-178 exam dumps 070-178
NO.8 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD
Microsoft demo 070-178 070-178 070-178 070-178 study guide
NO.9 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C
Microsoft 070-178 070-178
NO.10 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D
Microsoft 070-178 braindump 070-178 070-178 070-178 certification
Pass4Test offer the latest CAT-340 exam material and high-quality CUR-009 pdf questions & answers. Our JK0-U21 VCE testing engine and HP0-S33 study guide can help you pass the real exam. High-quality 3107 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.
Article Link: http://www.pass4test.com/070-178.html
没有评论:
发表评论