2013年6月12日星期三

GIAC certification GCPM exam questions and answers come out

If you use the Pass4Test GIAC GCPM study materials, you can reduce the time and economic costs of the exam. It can help you to pass the exam successfully. Before you decide to buy our GIAC GCPM exam materials, you can download our free test questions, including the PDF version and the software version. If you need software versions please do not hesitate to obtain a copy from our customer service staff.


GIAC certification GCPM exam has become a very popular test in the IT industry, but in order to pass the exam you need to spend a lot of time and effort to master relevant IT professional knowledge. In such a time is so precious society, time is money. Pass4Test provide a training scheme for GIAC certification GCPM exam, which only needs 20 hours to complete and can help you well consolidate the related IT professional knowledge to let you have a good preparation for your first time to participate in GIAC certification GCPM exam.


Pass4Test is a professional website. It focuses on the most advanced GIAC GCPM for the majority of candidates. With Pass4Test, you no longer need to worry about the GIAC GCPM exam. Pass4Test exam questions have good quality and good service. As long as you choose Pass4Test, Pass4Test will be able to help you pass the exam, and allow you to achieve a high level of efficiency in a short time.


We will free provide you part of the exercises of GIAC certification GCPM exam on the Internet to let you try to test our product's quality. After your trail you will find Pass4Test's exercises is the most comprehensive one and is what you want to.


Exam Code: GCPM

Exam Name: GIAC (GIAC Certified Project Manager Certification Practice Test)

Pass4Test's GIAC GCPM exam training material is the best training materials on the Internet. It is the leader in all training materials. It not only can help you to pass the exam , you can also improve your knowledge and skills. Help you in your career in your advantage successfully. As long as you have the GIAC GCPM certification, you will be treated equally by all countries.


In the past few years, GIAC certification GCPM exam has become an influenced computer skills certification exam. However, how to pass GIAC certification GCPM exam quickly and simply? Our Pass4Test can always help you solve this problem quickly. In Pass4Test we provide the GCPM certification exam training tools to help you pass the exam successfully. The GCPM certification exam training tools contains the latest studied materials of the exam supplied by IT experts.


GCPM Free Demo Download: http://www.pass4test.com/GCPM.html


NO.1 You are the program manager for your project. You are working with the project managers regarding
the procurement processes for their projects. You have ruled out one particular contract type because it is
considered too risky for the program. Which one of the following contract types is usually considered to be
the most dangerous for the buyer?
A. Cost plus incentive fee
B. Time and materials
C. Cost plus percentage of costs
D. Fixed fee
Answer: C

GIAC exam simulations   GCPM   GCPM   GCPM exam simulations

NO.2 You work as a project manager for Xxxx Inc. Which of the following processes will you use to formalize
the acceptance of the completed project deliverables?
A. Verify scope
B. Report performance
C. Expert judgment
D. Perform quality control
Answer: A

GIAC original questions   GCPM test   GCPM   GCPM questions

NO.3 You work as a project manager for BlueWell Inc. Which of the following techniques will you use to
determine whether particular work can best be accomplished by the project team or must be purchased
from the outside sources?
A. Expert Judgment
B. Make-or-Buy Analysis
C. Contract Types
D. Procurement Negotiations
Answer: B

GIAC test answers   GCPM   GCPM braindump   GCPM   GCPM braindump   GCPM

NO.4 You work as a project manager for Xxxx Inc. You are performing steps to carry out and finish the
project according to the measures drawn through the planning stage. Which of the following stages of the
project are you working on?
A. Monitoring and controlling
B. Closing
C. Initiation
D. Execution
Answer: D

GIAC   GCPM pdf   GCPM   GCPM questions   GCPM questions

NO.5 You work as a project manager for Xxxx Inc. You have to subdivide project
deliverables and project work into smaller, more manageable components. Which of the following
processes will you use to perform the above task?
A. Create WBS
B. Verify scope
C. Control scope
D. Define activities
Answer: A

GIAC exam dumps   GCPM exam dumps   GCPM dumps   GCPM   GCPM   GCPM study guide

NO.6 Charlie has just completed the project according to the terms of the contract. She and the customer
are completing a walk through of the project deliverables, and the customer is asking for changes to the
deliverables before she'll accept the product. What project management process should manage the
documented change request that may come from scope verification?
A. Scope management
B. Perform integrated change control
C. Control Scope
D. Control change control
Answer: B

GIAC test questions   GCPM   GCPM   GCPM   GCPM exam simulations

NO.7 You work as a project manager for Xxxx Inc. You are working on several projects. Your projects vary in
size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can
compare relative schedule and cost performance of each project. Which of the following components of
EVM provide measures of schedule and cost performance that are not affected by the size of the project?
A. BAC and EAC
B. CPI and SPI
C. CV and SV
D. PV and EV
Answer: B

GIAC certification   GCPM   GCPM   GCPM   GCPM questions   GCPM braindump

NO.8 You are a new Project Manager that has been entrusted with a software development project that is in
progress. A sub-contracting company has been awarded a cost reimbursable contract to do the
development work on this project, and the project has been completed. While trying to close this
procurement, you discover that still there are some unresolved claims. However, the sub contract
company does not accept that these claims are unresolved. Which of the following is the best method for
reaching the final equitable settlement?
A. Litigation
B. Mediation
C. Direct negotiation
D. Alternative dispute resolution
Answer: C

GIAC certification training   GCPM   GCPM exam simulations   GCPM

NO.9 Which of the following components of EVA is described in the statement below?
"It is a measure of how much of the project value has been earned so far through completed work, that is,
the budgeted cost of the work that has been performed through the project status date."
A. PV
B. AC
C. SV
D. EV
Answer: D

GIAC   GCPM   GCPM exam simulations   GCPM

NO.10 You work as a project manager for Xxxx Inc. You report the project details directly to the vice president
and the administrator of your organization. In which of the following types of organization structures are
you working?
A. Functional
B. Matrix
C. Jury
D. Projectized
Answer: B

GIAC certification   GCPM study guide   GCPM   GCPM test questions

NO.11 You work as a project manager for Xxxx Inc. You are in the project kickoff meeting. Which of the
following documents are reviewed during the project kickoff meeting?
Each correct answer represents a complete solution. Choose all that apply.
A. Project budget
B. Project WBS
C. Project charter
D. Project scope
Answer: A,C,D

GIAC answers real questions   GCPM test answers   GCPM   GCPM test answers   GCPM exam prep   GCPM demo

NO.12 You are the project manager for your organization. Marcy, a project stakeholder, is demanding that you
add some deliverables to your project scope for free. You explain to Marcy that it's too late in the project
execution to consider adding these deliverables, as most of the software your project team is creating is
nearly done. Marcy and you escalate the issue to management.
Management decides that you will add the deliverables to the project scope if Marcy pays a significant fee
and allows you additional time to complete the project. What conflict resolution method has management
offered?
A. Issue management
B. Compromising
C. Forcing
D. Confronting
Answer: B

GIAC   GCPM exam   GCPM   GCPM   GCPM

NO.13 You work as a project manager for Xxxx Inc. You are performing a task to generate a hierarchical list of
resources related by function and resource type that is used to facilitate planning and controlling of project
work. Which of the following components of project management will you use to accomplish the above
task?
A. PERT chart
B. RBS
C. Gantt chart
D. WBS
Answer: B

GIAC certification   GCPM exam dumps   GCPM answers real questions   GCPM   GCPM   GCPM exam dumps

NO.14 You are the project manager of the NHT Project. This project has 12,345 office doors to install
throughout a campus. Each of the doors costs the project $456 and requires special hardware to
electronically lock and open the doors. You've gathered the project team before they begin the installation
for a hands-on training. As a group you and the project team install 50 doors following a checklist of
instructions so that every door will be installed exactly the same throughout the campus and with minimal
waste. This is an example of what project execution technique?
A. Preventive action
B. Implemented corrective action
C. Quality control
D. Defect repair validation
Answer: A

GIAC certification training   GCPM braindump   GCPM   GCPM   GCPM certification training

NO.15 You are a Project Manager in your organization who is managing a considerably huge budget project
to develop new software. Considering the varied nature of your stakeholder group, you would like to put
together a plan as to what information the stakeholders need, and how to provide that information. What
is the document that you would need, and as part of which process group would you achieve this?
A. Communications Management Plan, Execution Process group
B. Project Management Plan, Planning Process Group
C. Communications Management Plan, Planning Process Group
D. Project Management Plan, Initiating Process Group
Answer: C

GIAC   GCPM   GCPM original questions   GCPM   GCPM

NO.16 Which of the following is described in the statement below?
"It is a tool that defines a project and groups the project's discrete work elements in a way that helps
organize and define the total work scope of the project."
A. WBS
B. RBS
C. Gantt chart
D. Critical path
Answer: A

GIAC   GCPM   GCPM

NO.17 Which of the following are the characteristics of a project?
Each correct answer represents a complete solution. Choose all that apply.
A. Its success is measured by evaluating whether it meets or exceeds expectations of the stakeholders.
B. It is temporary in nature and has a definite beginning and ending date.
C. It is completed when the project goals are achieved.
D. It is common in nature.
Answer: A,B,C

GIAC certification   GCPM   GCPM exam   GCPM

NO.18 Which of the following is described in the statement below.?
"It is a group of sequential and related project phases that are defined by the organization and control
needs of the management or organizations concerned with the project, the nature of the project itself, and
the application area."
A. Verify scope
B. Project charter
C. Activity list
D. Project life cycle
Answer: D

GIAC certification training   GCPM test questions   GCPM   GCPM questions   GCPM certification training   GCPM

NO.19 You work as a project manager for Xxxx Inc. A new project has been proposed to change all keyboards
of every computer in your organization. There are 1,600 keyboards that will need to be removed and
replaced with wireless keyboards. What document will you first need to start this project?
A. Project risk statement
B. Risk register
C. Project charter
D. Contract for new keyboards
Answer: C

GIAC certification   GCPM exam dumps   GCPM   GCPM test

NO.20 You are using the PDCA model to determine, implement, monitor, control, and maintain Information
Security Management System or ISMS. You have to evaluate the new processes and match up to the
results against the probable results to determine the differences. In which of the following phases of the
PDCA are you working?
A. Do
B. Act
C. Plan
D. Check
Answer: D

GIAC   GCPM answers real questions   GCPM   GCPM   GCPM practice test

NO.21 Which of the following processes describes the statement below?
"It consists of the processes required to ensure that the project contains all the work required to complete
the project effectively."
A. Project communications management
B. Project scope management
C. Risk management
D. Project human resource management
Answer: B

GIAC   GCPM   GCPM   GCPM exam

NO.22 You are in a project to create a Website. Your project team has met a few times and you're working
with them to develop the project's WBS. Jan, a marketing expert, is in disagreement with Larry over how
the Website should function. Gary and Gina are in disagreement over who'll take the lead on the design of
the software for the Website. Mark, Mary, and Martha are all bickering about the photo management
approach for the Website's pictures. What stage of team development is your project team currently in?
A. Forming
B. Storming
C. Performing
D. Norming
Answer: B

GIAC certification training   GCPM pdf   GCPM   GCPM   GCPM

NO.23 Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the
project planning processes is now coming into fruition. What individual should respond to the risk with the
preplanned risk response?
A. Diane
B. Risk owner
C. Subject matter expert
D. Project sponsor
Answer: B

GIAC certification training   GCPM test   GCPM pdf   GCPM original questions

NO.24 You work as a project manager for Xxxx Inc. You are working on a project that has a budget of
$805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have
actually spent $430,000 of the budget. Management wants to know the project's cost performance index.
Which of the following values will you report?
A. 0.87
B. 0.80
C. 0.84
D. 0.86
Answer: C

GIAC study guide   GCPM   GCPM exam dumps   GCPM

NO.25 Which of the following processes formally permits the initiation of a project and marks the kickoff for all
consequent development activities to begin?
A. Develop project charter
B. Develop project management plan
C. Develop project scope statement
D. Develop project team
Answer: A

GIAC   GCPM   GCPM original questions   GCPM   GCPM test questions

NO.26 Which of the following are the characteristics of the project life cycle?
Each correct answer represents a complete solution. Choose all that apply.
A. Cost and staffing are low at the start, are high as the work is carried out, and decrease as the project
comes towards the end.
B. Stakeholders influences, risk, and uncertainty are at peak in the beginning of the project.
C. Skills to influence the final characteristics of the project's product, without much impact on cost, is at
peak in the beginning of the project and reduces as the project progresses towards completion.
D. It is limited by constraints, including resource constraints.
Answer: A,B,C

GIAC dumps   GCPM   GCPM   GCPM   GCPM   GCPM study guide

NO.27 James works as the project manager for a software project. He and his team are on the Direct and
Manage Project Execution process. All of the following are inputs of this process except for which one?
A. Project charter
B. Organizational process assets
C. Enterprise environmental factors
D. Approved environmental requests
E. Project management plan
Answer: A

GIAC certification   GCPM dumps   GCPM original questions   GCPM demo

NO.28 Which of the following techniques is described in the statement below?
"It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid
of any resource limitations by performing a forward and backward pass analysis through the schedule
network."
A. Resource utilization
B. Critical path method
C. Critical Chain method
D. Resource leveling heuristic
Answer: B

GIAC pdf   GCPM   GCPM   GCPM answers real questions   GCPM exam

NO.29 You work as a project manager for Xxxx Inc. Which of the following stages of the process group, if not
performed well by you, is unlikely that the project will be successful in meeting the business needs?
A. Monitoring and controlling
B. Initiation
C. Executing
D. Planning and design
Answer: B

GIAC answers real questions   GCPM   GCPM certification training   GCPM original questions

NO.30 Which of the following processes formally permits the initiation of a project and marks the kickoff for all
consequent development activities to begin?
A. Develop project scope statement
B. Develop project management plan
C. Develop project charter
D. Develop project team
Answer: C

GIAC exam   GCPM braindump   GCPM

If you want to through the GIAC GCPM certification exam to make a stronger position in today's competitive IT industry, then you need the strong expertise knowledge and the accumulated efforts. And pass the GIAC GCPM exam is not easy. Perhaps through GIAC GCPM exam you can promote yourself to the IT industry. But it is not necessary to spend a lot of time and effort to learn the expertise. You can choose Pass4Test's GIAC GCPM exam training materials. This is training product that specifically made for IT exam. With it you can pass the difficult GIAC GCPM exam effortlessly.